How to Request a Hotel Furniture Quotation: Information a Manufacturer Needs from You
A clear RFQ is the fastest route to an accurate hotel furniture quotation. This checklist shows what to send a manufacturer so offers are complete and easy to compare.
A reliable hotel furniture quotation depends on the quality of the information you send. If a manufacturer has to guess at dimensions, finishes or delivery terms, the price will contain assumptions, and those assumptions are where budget surprises begin. This guide sets out the information a hotel furniture manufacturer in Turkey, or anywhere else, needs in order to quote accurately.
It is written for owners, procurement managers, designers and contractors preparing an RFQ for hotel furniture in Europe, the Middle East and neighbouring markets. Use it as a checklist before you send your enquiry.
Why the quality of your RFQ decides the quality of the quote
Custom hotel furniture is priced from drawings, specifications and quantities. A vague enquiry produces a vague offer, often with broad exclusions and allowances that are hard to compare with other bidders.
A well-prepared request does three things:
- It lets the manufacturer price the real scope instead of a rough estimate.
- It makes offers from different suppliers comparable line by line.
- It reduces revisions, which saves time on both sides before you place an order.
You do not need a perfect package at the first stage. Even so, the more complete it is, the more useful the answer will be.
Core documents to include in your RFQ
Drawings and design intent
Send whatever stage of design you have reached. Concept drawings, interior design layouts, elevations and sections all help. If detailed joinery drawings exist, include them in PDF and, where possible, DWG format.
If you only have mood boards and reference images, say so. A manufacturer can still give a budget-level estimate, but you should treat it as indicative until drawings are developed. Our article on custom hotel furniture from concept drawings to production explains how that development stage works.
Room schedule and furniture list
A room schedule is the backbone of any FF&E tender package. It should show each room type, the number of rooms of that type, and the furniture items in each one. A typical guest room list includes the bed base or headboard, bedside tables, desk and chair, wardrobe, luggage rack, TV unit and minibar cabinet.
List public areas and food and beverage spaces separately, because their construction and finishing requirements usually differ from guest rooms.
Bill of quantities
Where you have one, send a bill of quantities (BOQ) with item codes, descriptions and quantities. Using the same item codes throughout drawings, specifications and the quote avoids confusion later. If you are comparing several suppliers, ask all of them to price against the same BOQ format.
Specification details that change the price
Materials and finishes are among the biggest cost drivers in hotel furniture. State what you require rather than leaving it open.
- Board and structure: plywood, MDF or particleboard, and any emission class required for the destination.
- Surfaces: HPL, veneer, lacquer, PU coating or solid wood, with colour references or physical samples where available.
- Edging: ABS, solid wood or other, and any corner radius requirements.
- Upholstery: fabric type, leather or faux leather, foam density if specified, and who supplies the fabric.
- Hardware: hinge and runner type, soft-close requirements, locks and handles, including any brand preferences.
- Stone, glass and metal: tops, mirrors, inserts and metalwork that form part of the furniture.
If your designer has named a specific material or brand, mention it. If equivalents are acceptable, say that too, because it can open up more cost-effective options.
Compliance and testing requirements
Fire performance, emission limits and any strength testing should be stated in the RFQ, not discovered after award. Requirements differ between a hotel in Germany, France or the UK and one in Saudi Arabia or the UAE, and they can affect board, foam and fabric choices as well as lead time.
Tell the manufacturer which standards or authority requirements apply, and whether test reports must be supplied. For more on this topic, see our guide to fire safety and compliance for hotel furniture in Europe and the Middle East.
Delivery terms, location and timing
Freight is part of the total cost, so the manufacturer needs to know what you want included. Specify:
- The Incoterm you want quoted, such as EXW, FOB, CIF or DAP.
- The destination country, city and port, or the site address for delivered terms.
- Whether delivery is in one shipment or in phases, for example floor by floor.
- Your target delivery window and the construction programme it depends on.
- Whether on-site installation is required, and if so, the site conditions and access.
It helps to quote the same Incoterm from every bidder. If one offer is EXW and another is DAP, the totals cannot be compared fairly. Our article on Incoterms for hotel furniture orders explains the differences.
Packing, labelling and installation scope
Say whether you need export packing, room-by-room labelling and a packing list that matches your room codes. These details speed up unloading and installation, and they affect the packing cost.
If installation is required, clarify whether it should be done by the manufacturer's crew or by your contractor, who handles lifting and storage on site, and how snagging will be managed.
Samples, mock-up room and approvals
Indicate whether you expect material samples, a prototype or a full mock-up room before mass production, and who will approve each stage. Mock-up rooms and sample approvals are usually priced and scheduled separately from the main order, so it is better to include them in the RFQ from the start.
Also describe your approval workflow: who signs shop drawings, how many review rounds you expect, and the response time you can commit to. Approval speed has a direct effect on the production schedule.
Commercial information the manufacturer will ask for
Besides technical details, share the commercial framework so the offer fits your project:
- Project name, location and type of hotel, including the star category or brand standard.
- Total number of rooms and the planned opening date.
- Preferred payment structure, such as deposit and milestone payments.
- Quotation validity period and the currency you want to receive.
- Tender deadline and the name of the contact person for questions.
You do not have to disclose your target budget, but a rough range can help a manufacturer suggest suitable constructions and value engineering options.
A simple RFQ checklist
| Item | What to send |
|---|---|
| Drawings | Layouts, elevations, joinery details (PDF and DWG) |
| Quantities | Room schedule, furniture list or BOQ |
| Materials | Boards, finishes, upholstery, hardware, references or samples |
| Compliance | Fire, emission and testing requirements for the destination |
| Delivery | Incoterm, destination, phasing, target dates |
| Services | Packing, labelling, installation, mock-up room |
| Commercial | Payment terms, validity, currency, tender deadline |
How to make quotes comparable
When you run a tender, give every supplier the same documents and the same deadline. Ask them to price against one BOQ format, state their exclusions clearly and list any assumptions. Differences between offers will then reflect real differences in construction, materials and service rather than differences in interpretation.
Watch for allowances and provisional sums. They are sometimes used to keep a headline price low, and they can grow once the real scope is confirmed.
What to expect after you send your request
A competent manufacturer will review the package and usually come back with clarification questions before pricing. This is a good sign, not a delay. Questions about a missing dimension or an unclear finish show that the quote will be built on facts.
Timing and cost depend on the project size, the level of detail in your drawings and the materials chosen, so a precise timeline is only possible once the scope is reviewed.
Next step
If you are preparing an RFQ for a new hotel or a renovation, send us your drawings, room schedule or BOQ. We will review them and respond with questions, material suggestions and a quotation for your project.
Sıkça Sorulan Sorular
What information is needed to get a hotel furniture quotation?
At minimum, send drawings or layouts, a room schedule or BOQ, material and finish preferences, the destination and the Incoterm you want quoted. Fire and emission requirements, installation scope and your target delivery dates also help. The more complete the package, the more accurate the quotation.
Can I request a quote if I only have concept designs?
Yes. A manufacturer can give an indicative budget estimate from concept drawings, mood boards and a room schedule. It will carry more assumptions, so treat it as a planning figure and ask for a firm quotation once shop-level drawings and specifications are available.
Which Incoterm should I ask for in an RFQ?
It depends on how much of the logistics you want to manage. EXW and FOB leave freight and import to you, while CIF and DAP include more of the transport. Whichever you choose, ask every bidder to quote the same term so offers can be compared fairly.
How do I compare quotations from different furniture suppliers?
Send every supplier the same drawings, BOQ and deadline, and request the same Incoterm. Then compare materials, hardware, exclusions, assumptions and services such as packing and installation. A lower total can simply mean a narrower scope or lighter construction.
Should I include a mock-up room in the RFQ?
Yes, if you plan to approve the design physically before production. Mock-up rooms are usually priced and scheduled separately from the main order, so stating the requirement in the RFQ avoids later scope and timeline disputes.
How long does it take to receive a hotel furniture quotation?
It depends on the size of the package and the completeness of your documents. A clear RFQ with drawings and a BOQ is generally quicker to price. Large or custom packages may need clarification rounds before a final offer is issued.