What Is Included in an Ex-Works Furniture Price from a Turkish Factory?
An ex-works quote covers the furniture and its export packing at the factory gate, but not the cost of getting it to your hotel. This guide shows what sits inside EXW and which steps you add to reach a landed price.
An ex-works furniture price Turkey quote covers the cost of making the furniture and preparing it for collection at the factory. It does not cover transport, export clearance, insurance, import duties or installation. To budget accurately, you need to know where the EXW price ends and where your own costs begin.
This guide breaks down what a typical EXW quote from a Turkish factory includes, what it usually leaves out, and how to build a landed cost at your hotel. Exact figures always depend on your project, so we focus on structure rather than numbers.
What EXW Means in Practice
EXW (Ex Works) is an Incoterm under which the seller's responsibility ends once the goods are made available at the seller's premises. From that point, the buyer carries the cost and risk of loading, transport, export formalities, import formalities and delivery. In a hotel project, this makes EXW the most basic price basis and the easiest for comparing factories on the manufacturing cost alone.
A factory gate price is useful precisely because it isolates the production cost. It is, however, only the first line of your total budget.
What an EXW Hotel Furniture Quote Normally Includes
Scopes differ between suppliers, so confirm each item in writing. A clear EXW quote from a factory typically covers the following.
- Materials: boards, veneers, HPL or laminates, solid timber elements, edging and finishes as listed in the specification.
- Hardware and components: hinges, drawer runners, handles, fixings, and any integrated items such as lighting or sockets if they are part of the scope.
- Upholstery and soft elements: fabrics, foam and leather for headboards, benches or seating, where included in the package.
- Labour and production: cutting, machining, assembly, finishing and in-factory quality checks.
- Export packing: protective wrapping, corner protection, cartons or crates suitable for the chosen transport mode. Always check whether this is included or priced separately.
- Labelling: room-by-room or item-by-item marking and a packing list, which helps on site later.
- Loading at the factory: in some quotes loading onto your truck is included, while strictly under EXW it remains the buyer's responsibility. Ask for clarity.
What Is Often Included Only if Stated
Some items sit in a grey area. They may appear in an EXW quote as separate lines or be left out entirely, so check them before you compare offers.
- Design support, shop drawings and revisions.
- The sample or mock-up room, including its shipping.
- Spare parts and extra stock of doors, handles or panels.
- Special testing or documents requested by the destination market.
- Fumigation or treatment of wooden packing where the destination requires it.
What an EXW Price Does Not Include
These are the costs that make the difference between a factory gate price and the real cost of a hotel opening.
- Inland transport from the factory to the port or border.
- Export customs clearance in Turkey (under strict EXW, the buyer arranges this, often through a freight forwarder).
- Main freight by sea, road, rail or air.
- Marine cargo insurance.
- Destination port or terminal charges.
- Import duties, VAT or equivalent taxes, and customs broker fees.
- Delivery from the destination port to the hotel site and offloading.
- Storage, if the building is not ready.
- Installation, snagging and removal of packing waste.
From EXW to Landed Price: The Cost Steps
A landed price is the total cost of having the furniture delivered to the hotel and ready to be installed. Think of it as a sequence of steps added to the EXW figure.
| Step | What it covers | Who usually arranges it under EXW |
|---|---|---|
| 1. EXW price | Furniture, hardware, finishes, export packing | Factory |
| 2. Loading and inland haulage | Collection from Istanbul to port or border | Buyer or forwarder |
| 3. Export clearance | Turkish customs formalities and documents | Buyer or forwarder |
| 4. Main freight | Container, truck or air shipment | Buyer or forwarder |
| 5. Insurance | Cargo cover during transit | Buyer |
| 6. Import clearance | Duties, taxes, broker and port charges | Buyer |
| 7. Final delivery | Transport to site, offloading, storage | Buyer or contractor |
| 8. Installation | Assembly, fixing, adjustments, snagging | Installer, factory team or local contractor |
Each step varies by country, route and season. We therefore recommend asking a forwarder for a destination quotation early, rather than adding a rough percentage to the factory price.
EXW, FOB, CIF and DAP Side by Side
If your team prefers fewer moving parts, you can ask for a different Incoterm. The same furniture will simply carry more of the logistics inside the price.
| Incoterm | Seller covers up to | Buyer still handles |
|---|---|---|
| EXW | Goods ready at the factory | Almost everything from loading onwards |
| FOB | Export clearance and loading on board at the named port | Sea freight, insurance, import and delivery |
| CIF | Freight and insurance to the destination port | Import clearance and final delivery |
| DAP | Delivery to the named place, ready for unloading | Import duties and taxes, unloading |
Comparing quotes on different Incoterms is a common source of confusion. Convert them to one basis, ideally landed cost, before judging which offer is better.
Common Mistakes When Reading an EXW Quote
- Comparing EXW with a delivered price. A lower EXW figure may simply leave out costs that another supplier has already included.
- Ignoring packing. Export-grade packing protects the investment, and weak packing leads to damage claims later.
- Forgetting volume. Furniture is bulky. Freight depends on packed volume and weight, not only on the number of rooms.
- Assuming installation is included. It is normally a separate line, even if the factory offers on-site teams.
- Overlooking validity. Check how long the price holds and how raw material changes are handled.
How to Ask for a Clear Quote
The more precise your enquiry, the clearer the answer. When you request an EXW hotel furniture quote, send your room schedule, drawings or sketches, finish references and destination country. State whether you want only EXW or also FOB, CIF or DAP options. Ask for a line-by-line list so that every export furniture quote item is visible, including packing, labelling and documents.
With that information, we can show what is included in the factory price and what you should plan separately for your destination.
Next Step
If you are planning a hotel project anywhere in the world, send us your drawings or room schedule. Palmiye will prepare a clear quotation showing exactly what the factory price includes, with shipping options for your destination so you can work out your landed cost.
Sıkça Sorulan Sorular
Does an ex-works price include shipping?
No. An ex-works price covers the furniture and its export packing at the factory. Transport, customs clearance, insurance, duties and delivery to your hotel are added separately, either arranged by you or priced under another Incoterm such as FOB, CIF or DAP.
Is export packing included in an EXW furniture quote?
It usually is for export orders, but you should confirm it in writing. Packing method, crates and labelling can be listed as separate lines. Ask the factory to state exactly what protection is included for your transport mode.
Who handles Turkish export clearance under EXW?
Strictly speaking, the buyer does, usually through a freight forwarder. Many factories help in practice, but this should be agreed in the quotation. If you prefer the factory to manage it, ask for an FOB, CIF or DAP price.
How do I calculate the landed price from an EXW quote?
Add each step after the factory gate: inland haulage, export clearance, main freight, insurance, import duties and taxes, port charges, final delivery and installation. Request a destination quotation from a forwarder rather than relying on a rough percentage.
Is EXW the cheapest way to buy hotel furniture?
It shows the lowest headline figure because logistics are excluded, but total cost depends on your freight and import arrangements. Compare offers on a landed basis to see the real difference between suppliers.